Project History and Purpose: Creel Ditch is an incised drainage channel draining a 4.7-square mile watershed of row crops and pasture (69%), water and wetlands (16%), forest (8%), and low and high density development (6%). In 2006, The Nature Conservancy – Upper St. Joseph Project Office received a grant from The Joyce Foundation to implement conservation practices in the Creel Ditch watershed to reduce sedimentation to the downstream receiving system, Fish Creek. Fish Creek is the only known location where the White Cat’s Paw Pearly mussel, a federally endangered species, is currently found. Prior to construction of the two-stage channel the existing trapezoidal channel had mass bank failures scattered throughout much of the project reach impacting water quality and habitat.   The Nature Conservancy worked with 7 landowners along Creel Ditch to implement 5,200-feet of two-stage channel. Pre- and post-construction monitoring suggested nitrate, phosphorus, and total suspended sediment loads were reduced after two-years and fish and macro-invertebrate communities were improved relative to pre-construction conditions. Ammonia concentrations and substrate composition were not significantly different after two-years. 

Creel Ditch Pre-Construction
Creel Ditch prior to two-stage modifications.

Creel Ditch During Construction
Construction of Creel Ditch.

Creel Ditch Post-Construction
Creel Ditch several weeks after construction.

Creel Ditch Flooding
Creel Ditch under flood conditions shortly after construction.

SITE PHYSICAL CHARACTERISTICS
Drainage Area
: 4.7-square miles
Channel Slope: 0.3%
Project Length: 5200-feet (Reach 1 – 1200-feet; Reach 2 – 4000-feet)

PROJECT COSTS:
Reach 1
Earthwork Cost
: $14,546
- Mobilization: $0
- Site Preparation: $0
- Soil Excavation, Hauling, and Disposal: $14,546
- 4,156-cubic yards @ $3.50 per cubic yard
- 3.5-cubic yards per linear foot of channel
- $12.12 per linear foot
Outlet protection and erosion control: $0
Seed and Seeding: $0
Repairs: $0
Engineering, survey, and inspection: $0 (design completed in-kind by OSU)
Total Cost: $14,546
Cost per linear foot: $12.12

Reach 2
Earthwork Cost
: $87,686
- Mobilization: $0
- Site Preparation: $0
- Soil Excavagtion, Hualing, and Disposal: $87,686
- 25,052-cubic yards @ $3.50 per cubic yard
- 6.3-cubic yards per linear foot of channel
- $21.92 per linear foot
Outlet protection and erosion control: $0
Seed and Seeding: $0
Repairs: $0
Engineering, survey, and inspection: $0 (design completed in-kind by OSU)
Total Cost: $87,686
Cost per linear foot: $21.92

 